Final evaluation of the hot hydrotest by ÚJD SR

The hot hydrotest of Unit 3 of NPP Mochovce 3 & 4 (MO3&4) was carried out from 21 December 2018 until 15 March 2019. During the hot hydrotest, the reactor and its cooling circuits were heated up to an operating temperature of 260 °C and pressurized to 12.2 MPa. At the end, the entire primary […]

Temporary suspension of the administrative proceedings, Unit 4

Temporary suspension of the administrative proceedings, Unit 4 The Nuclear Regulatory Authority of the Slovak Republic (ÚJD SR, Authority) by its decision No. 205/2019 temporarily suspended the administrative proceeding in the issue of authorization for commisioning of Unit 4 of Mochovce NPP and the connected administrative proceeding in the issue of authorization for treating the […]

Prolongation of the deadline for decision, Unit 3

Prolongation of the deadline for decision, Unit 3 Based on the demand of the first-level administrative authority, the chairperson of the Authority prolonged the deadline for decision making in the issue of authorization for commissioning of Unit 3 and treating the radioactive waste and spent nuclear fuel for Unit 3 for 6 months. The reason […]

Preliminary Assessment of Hot Hydrotest of MO34, Unit 3

From December 21, 2018 to March 15, 2019, hot hydrotest was carried out at Unit 3 of NPP Mochovce 3 & 4 (EMO34). Hot hydrotest is the last comprehensive test of unit equipment prior to its commissioning. During the hot hydrotest, the most important technological equipment of the Unit was tested: reactor (without nuclear fuel, […]

Information on the Course of the Hot Hydrotest and the Next Steps in the Process of Preparing Unit 3 of NPP Mochovce 3 & 4 for Commissioning

Hot Hydrotest: From December 21, 2018 to March 15, 2019, hot hydrotest was carried out at Unit 3 of NPP Mochovce 3 & 4 (EMO 3 & 4). Hot hydrotest is the last comprehensive test of unit equipment prior to its commissioning. During the hot hydrotest, the most important technological equipment of the Unit was […]

Extension of the period for decision (commissioning of NI, RAW and SNF management)

Extension of the period for decision is justified by the large amount of inspection activities, that are performed by the inspectors of ÚJD SR on the Unit 3 of MO34 respectively that will need to be performed during the testing of systems and facilities of MO34 Unit 3. The performance of these inspections is necessary […]

Appeal proceeding (FFN)

One of the participants of the administrative proceeding (the organization Global 2000 – Friends of the Earth, Neustiftgasse 36, A-1070 Wien, hereinafter Global 2000) has pursuant to Section 53 of the Administrative Code filed an appeal against the decisions of Nuclear Regulatory Authority of the Slovak Republic (ÚJD SR): No. 277/2018 from 29 October 2018, […]

Notice on the continuation of administrative proceeding for fresh fuel node

Slovenské elektrárne, a. s., has amended on 22 June 2018 the application in the matter of issuing an authorization for management of nuclear materials in nuclear installation MO 3 & 4 within the scope of handling and storage of fresh nuclear fuel in the fresh fuel node and relevant applications (commissioning withing the scope of […]

Temporary suspension of the administrative proceeding

After the preliminary evaluation of the documentation relevant to the application of SE, a. s. for issuing an authorization for commisionig of nuclear installation Mochovce Unit 3 and 4, SE, a. s. have also applied for the issuing of an authorization for early use of a building, issuing of an authorization for management of radioactive […]

Postponement of the deadline for submission of comments on the comments for the decision

Based on the request of one of the participants in the administrative proceeding Nuclear Regulatory Authority of the Slovak Republic postpones the deadline for submitting comments on the documentation for the decision on fresh fuel node of MO 3 & 4. The original deadline for submitting written comments was 27 August 2018 and the Authority […]