Information on the Course of the Hot Hydrotest and the Next Steps in the Process of Preparing Unit 3 of NPP Mochovce 3 & 4 for Commissioning

Hot Hydrotest: From December 21, 2018 to March 15, 2019, hot hydrotest was carried out at Unit 3 of NPP Mochovce 3 & 4 (EMO 3 & 4). Hot hydrotest is the last comprehensive test of unit equipment prior to its commissioning. During the hot hydrotest, the most important technological equipment of the Unit was […]

Extension of the period for decision (commissioning of NI, RAW and SNF management)

Extension of the period for decision is justified by the large amount of inspection activities, that are performed by the inspectors of ÚJD SR on the Unit 3 of MO34 respectively that will need to be performed during the testing of systems and facilities of MO34 Unit 3. The performance of these inspections is necessary […]

Appeal proceeding (FFN)

One of the participants of the administrative proceeding (the organization Global 2000 – Friends of the Earth, Neustiftgasse 36, A-1070 Wien, hereinafter Global 2000) has pursuant to Section 53 of the Administrative Code filed an appeal against the decisions of Nuclear Regulatory Authority of the Slovak Republic (ÚJD SR): No. 277/2018 from 29 October 2018, […]

Notice on the continuation of administrative proceeding for fresh fuel node

Slovenské elektrárne, a. s., has amended on 22 June 2018 the application in the matter of issuing an authorization for management of nuclear materials in nuclear installation MO 3 & 4 within the scope of handling and storage of fresh nuclear fuel in the fresh fuel node and relevant applications (commissioning withing the scope of […]

Temporary suspension of the administrative proceeding

After the preliminary evaluation of the documentation relevant to the application of SE, a. s. for issuing an authorization for commisionig of nuclear installation Mochovce Unit 3 and 4, SE, a. s. have also applied for the issuing of an authorization for early use of a building, issuing of an authorization for management of radioactive […]

Postponement of the deadline for submission of comments on the comments for the decision

Based on the request of one of the participants in the administrative proceeding Nuclear Regulatory Authority of the Slovak Republic postpones the deadline for submitting comments on the documentation for the decision on fresh fuel node of MO 3 & 4. The original deadline for submitting written comments was 27 August 2018 and the Authority […]

Removal of the application deficiencies

With issuing of the decision No. 334/2018 Nuclear Regulatory Authority of the Slovak Republic has temporary suspended the administrative proceeding for issuing the authorization for commisioning of MO 3 & 4 and other relevant authorizations and it has also set the condition of continuation in the proceeding – removal of identified deficiencies in the documentation. […]

Rules for Consulting

To facilitate familiarization with the documentation in the currently ongoing administrative proceedings concerning the application of SE, a. s., to license commissioning of the nuclear installation of NPP Mochovce Units 3 & 4, and related authorizations, the Nuclear Regulatory Authority of SR has set up a separate workplace at the site of Nuclear Power Plants […]

Notice of Documentation Disclosure in Administrative Proceedings NPP Mochovce 3 & 4

To enable the public to become familiar with the documentation in the currently ongoing administrative proceeding concerning the application of SE, a. s., for license for commissioning of a nuclear installation of Mochovce Units 3 & 4 and related authorizations, the Nuclear Regulatory Authority of SR established an independent workplace at site of the nuclear […]

Change of the deadline for issuing Decision – Extension of the period

Proceeding No.: 3720-2016 In the current administrative procedure of the Authority regarding the application by SE, a. s., to issue authorization for commissioning of the nuclear installation Mochovce Units 3 & 4, to issue permit for early use of the project, to issue authorization for management of radioactive waste and spent nuclear fuel, and to […]