4.5.6 ÚJD requirements for safety improvement of WWER-440/V-213 at NPP Mochovce


For a historical overview of the requirements on safety improvement of WWER-440/V-213 reactors at Mochovce, see National Report, September 1998.

In meeting ÚJD requirements, NPP Mochovce unit 1 was commissioned in 1998, and unit 2 of NPP Mochovce was commissioned in 1999-2000 while complying with start up stages and enhanced emphasis on the implementation of safety measures.

The extent and the time schedule of the implementation of safety measures at NPP Mochovce was presented to ÚJD for review on 29 November, 1999. In December, ÚJD issued Decision No. 433/99 that set new dates for, and the extent of the implementation of safety measures.

Approval of NPP Mochovce unit 2 operation was granted by ÚJD by Decision No. 84/2000 setting, a.o. requirements on dates and the method of implementation of safety measures that had not been completed at the time of the unit start up. The current status of the implementation of safety measures is described in Chapter 2.3.3.3.