4.5.5 ÚJD requirements for WWER-440/V-213 NPP V-2 safety improvement


For a historical overview concerning requirements on safety improvement of WWER-440/V-213 reactors at Bohunice, see National Report, September 1998.

In 2000, ÚJD reviewed the document „Safety Concept of the Upgrading and Safety Improvement for NPP V-2“ presented by SE, a.s., the operator of the power plant. Having reviewed the document, ÚJD issued Decision No. 214/2000 instructing the operator to develop terms of reference for the individual measures contained in the Concept, including an implementation time schedule, so as to implement the individual measures depending on their category gradually by 2008. The principal measures whose implementation was imposed by Decision No. 214/2000 were taken by the operator in June 2001, who presented the document „Account of the Implementation of Recommendations on Safety Related Issues of NPP WWER440, model 213 from IAEA document EBP-WWER-03, and their Actual Status for NPP Bohunice units 3 and 4 .

Predchádzajúca kapitolaPredchádzajúca stranaOBSAHNasledujúca stranaNasledujúca kapitola