2.2.4 NPP V-2 units
safety improvement programs
The objective of
the operator is to not only maintain the present level of nuclear safety but also its
improvement as suggested by new knowledge and experience from NPP operation. To meet this
objective, „NPP V-2 Upgrading and Safety Improvement Programme“ was developed as
described in more detail in chapter 5.4. In this section, measures implemented so far are
summarized.
Selected actions relevant for NPP V-2 safety improvement which are in accordance with the
Safety Concept have priority. The individual actions have been planned to become
implemented during planned unit outages. So far, the following important safety and
upgrading measures have been implemented:
- upgrading of the upper distribution piping of SG feeding
water and feeding heads,
- installation of a pressurizer relief valve,
- first phase of the seismic reinforcements of reactor coolant
system loops,
- replacement of category I uninterruptible supply
accu-bateries,
- implementation of a new redundant power source at system 4
of category I uninterruptible power supply,
- introduction of symptom-oriented emergency operating
procedures,
- diagnostic systems for the monitoring of small leaks from
primary circuit equipment meeting LBB criteria,
- upgrading of the RC monitoring system (addition of a
redundant environmental contact unit), and replacement of secondary computer system,
- measure to prevent clogging of the emergency systems pump
suction and of spray system nozzles,
- installation of an automated fire extinguishing equipment
for reactor coolant pump compartment,
- replacement of all generator breakers,
- replacement of electric protections of 6 kV drives,
- installation of LFC terminals for remote control of electric
parameters from dispatching center,
- non-destructive tests:
The following measures have been/are being implemented :
 |
having increased the sensitivity
of the facility to reactor pressure vessel in-service inspections from the outside,
integral test was performed during the outage of NPP V-2 unit 4 and subsequently control
of unit 3 during 1999 EOH, |
 |
staff qualification follows
Slovak national standard STN EN 473 and is expected to be completed in 2002, |
 |
the programme of operation
defectoscopy of I&C lines (up to the first separating valve) connected to components
and of primary circuit pipe systems is going on, |
 |
operation testing of NPP V-2
equipment is going on according to the new guideline MN-14 that applies the most recent
knowledge and experience in the field of non-destructive tests, and contains operation
monitoring programs for all pipelines up to the first closing valve, |
 |
appropriate samples with
implanted material defects are being prepared in cooperation with VÚJE, |
 |
qualification of a system of
non-destructive testing according to IAEA guidelines is being prepared in cooperation with
VÚJE, |
- fire prevention
To improve fire safety and to resolve the safety-related problem, the following measures
have been implemented or are being implemented:
 |
a systematic analysis of
fire-related risk was conducted in 1998 based on which a fire project will be developed, |
 |
to prevent spreading of smoke
and fire, anti-fire flaps have been installed controlled by temperature in the
corresponding air conditioning system and being independent from the other systems of the
power plant, |
 |
cable partitions and closures at
MGU were coated with Dexaflamm, an fire resistant material. Wherever redundant cables
cannot be separated, certified foaming materials will be used to cover them, |
 |
fire resistant penetrations and
barriers are subject of regular inspections, |
 |
water guns to cool ceiling
structures were installed at the machine room, |
 |
semi-stable foam fire
extinguishing equipment was installed to main oil tanks of turbo generators and to the oil
systems of electric feed water pumps, |
 |
floors of cable channels with a
stable fire extinguishing equipment were insulated, |
 |
electric fire detection was
upgraded in electric buses and technological computer rooms, |
 |
a new firewall was built between
stand-by transformers AU01 and AU02, and the original firewalls between the unit and
branch transformers were extended, |
 |
junctions of 6 kV cables for
diesel generator station were replaced, |
 |
signaling of the fire doors
positions in cable channels of the main production building and external cable channels
was installed, |
 |
firefighting cards were
developed for the management of firefighting intervention by the plant fire brigade and
operating staff. |
A plant fire brigade is on duty around the
hour at the Bohunice site and able to intervene at any place within minutes.
The following actions are planned to be implemented during 2001:
- project documentation resulted from the Safety Concept,
- modification of emergency low-pressure and spray pumps
recirculation,
- modification - relocation of emergency feed water lines from
+14.7m.
    
|