3.8  INSPECTION AND ASSESSMENT ACTIVITIES AT NUCLEAR INSTALLATION:


NUCLEAR INSTALLATIONS OPERATED BY VUJE TRNAVA
 

There are two independent nuclear installations at the site of A-1 NPP operated by VUJE Trnava. One is an experimental incinerator of burnable solid and liquid radioactive waste, and the other is a pilot bituminization line. The incinerator was not operated in 1998, and on the bituminization line conditioning of concentrates coming from EBO V-1 NPP together with dowtherm (coming from A-1 NPP) was started.

Assessment activity

Assessment activity of UJD was concentrated on review of the safety documentation submitted by VUJE Trnava together with the application for approval to prolong the operation of the experimental incinerator and to process dowtherm with concentrates on the bituminization line and for experimental conditioning of sludges from EBO V-1 NPP by cementation.

Inspection activity

Inspection activity of UJD was focused especially on fire risks in conditioning of radioactive waste by bituminization.

 
 
© Nuclear Regulatory Authority of the Slovak Republic, 1999

WWW DESIGN    © INFELEN, 1999